MWatt Hubpower-sector data

← Tools

Operational guide · Brazil

Brazil grid connection journey for generation and load

This journey starts with what a project must actually accomplish — not with a product catalog. It identifies who moves each step, the timeline that can honestly be stated, and the failures that send projects backwards. Existing tools are linked; missing ones remain visible.

Small/medium (DG)

Connection journey — distributed generation

The full process, including steps without a tool yet

  1. 1

    Define the DG model and site

    Local, remote or shared self-consumption, or EMUC; site, ownership and source.

    Owner
    Project owner, supported by the designer
    Typical timeline
    Before equipment purchase or the access filing.
    What goes wrong
    The chosen model is incompatible with ownership, site rights or credit allocation.
  2. 2

    Assess resource and feasibility

    Solar resource, yield, CAPEX, tariff and return at the actual site.

    Owner
    Project owner, installer and advisers
    Typical timeline
    During feasibility; repeat after a change in site, tariff or capacity.
    What goes wrong
    Generic resource data and omitted losses, Fio B or connection costs distort returns.
  3. 3

    Check hosting capacity

    Indicative feeder capacity and utility-published data.

    Owner
    The utility publishes data; the project owner screens it
    Typical timeline
    Fast screening, but confirmation only arrives in the connection budget.
    What goes wrong
    An indicative map is treated as reserved capacity or approval.
  4. 4

    Compare TUSD/TUST and locational signals

    Tariff, contracted capacity, charges and the point's long-term economics.

    Owner
    ANEEL approves tariffs; the utility or ONS applies them; the project owner models them
    Typical timeline
    At site selection and again before contractual commitments.
    What goes wrong
    The model uses an old tariff cycle or ignores contracted capacity and charges.
  5. 5

    Prepare design and electrical studies

    Protection, flow, quality and documents consistent with capacity and voltage.

    Owner
    Project owner and licensed engineer; the utility assesses
    Typical timeline
    Variable with capacity, voltage and additional studies.
    What goes wrong
    Forms, diagrams, equipment and capacity contain inconsistent data.
  6. 6

    Run environmental and land permitting

    Scope, studies and permits with the competent environmental authority.

    Owner
    Project owner before the competent federal, state or municipal authority
    Typical timeline
    Variable by location, impact, study and requests for additional information; start early.
    What goes wrong
    An assumed exemption or early permit is mistaken for full permission to build and operate.
  7. 7

    Obtain registration or generation authorization

    The act depends on source, capacity and regulatory regime.

    Owner
    Project owner files; ANEEL regulates and issues the applicable act
    Typical timeline
    No single deadline; source, capacity and regime determine the procedure.
    What goes wrong
    The wrong procedure is used or authorization, access and permit data disagree.
  8. 8

    Find the channel and documents

    The responsible utility's portal, forms and technical standard.

    Owner
    Project owner files; the local utility receives and guides
    Typical timeline
    Before the formal request; verify current forms.
    What goes wrong
    The request goes to the wrong company, an informal channel or an obsolete form.
  9. 9

    Connection request and budget

    For Brazilian DG, the former access opinion now follows the connection-budget process.

    Owner
    Project owner submits a complete request; the utility assesses and issues
    Typical timeline
    REN 1,000: 15, 30 or 45 days depending on voltage, generation and works; defined circumstances can suspend the clock.
    What goes wrong
    Missing documents, reverse-flow analysis or consultation with another network disrupt the expected calendar.
  10. 10

    Build, commission and clear operation

    Connection works, protection, metering, telecoms, tests and operational release.

    Owner
    Project owner and grid owner execute their scopes; ONS participates where applicable
    Typical timeline
    Set mainly by required works and the contractual schedule; major reinforcements can take years.
    What goes wrong
    Interfaces lack an owner, or protection, metering, telemetry and tests are left until late.
  11. 11

    Activate and audit compensation

    Beneficiary units, metering, credits and Fio B charges.

    Owner
    The utility meters and bills; the account holder audits and maintains allocations
    Typical timeline
    After connection and during every billing cycle.
    What goes wrong
    Allocation is wrong, a beneficiary is missing or non-compensable charges were expected to disappear.

Large generator (transmission)

Connection journey — large generator

From site selection to operation on the Basic Grid/DIT

  1. 1

    Assess resource, land and constraints

    Energy resource, land, logistics, market and electrical proximity.

    Owner
    Project owner and specialist advisers
    Typical timeline
    Early development; revisit after changes to layout or connection point.
    What goes wrong
    A strong natural resource masks an unconnectable, unpermittable or insecure site.
  2. 2

    Check SIN export margins

    Indicative margin by busbar, queue and scenario — not a capacity reservation.

    Owner
    ONS publishes; the project owner compares points and scenarios
    Typical timeline
    Continuous screening using the latest publication; formal access must confirm it.
    What goes wrong
    Margins from different scenarios are added or the dashboard is treated as a positive opinion.
  3. 3

    Compare TUSD/TUST and locational signals

    Tariff, contracted capacity, charges and the point's long-term economics.

    Owner
    ANEEL approves tariffs; the utility or ONS applies them; the project owner models them
    Typical timeline
    At site selection and again before contractual commitments.
    What goes wrong
    The model uses an old tariff cycle or ignores contracted capacity and charges.
  4. 4

    Define MUST or contracted demand

    Transmission uses MUST; distribution uses demand under the applicable contract.

    Owner
    Project owner proposes; ONS or the utility assesses and contracts the applicable amount
    Typical timeline
    Defined before access and consolidated in the contract; phase it with the project ramp-up.
    What goes wrong
    Under-contracting creates exceedance exposure; over-contracting pays for idle capacity.
  5. 5

    Perform electrical studies

    Power flow, contingencies, short circuit, quality and applicable dynamics.

    Owner
    Project owner performs studies; ONS or the utility assesses them
    Typical timeline
    Iterative; repeat when the model, plant/load or point changes.
    What goes wrong
    An outdated model, mismatched assumptions or missing required cases creates a blocking issue.
  6. 6

    Run environmental and land permitting

    Scope, studies and permits with the competent environmental authority.

    Owner
    Project owner before the competent federal, state or municipal authority
    Typical timeline
    Variable by location, impact, study and requests for additional information; start early.
    What goes wrong
    An assumed exemption or early permit is mistaken for full permission to build and operate.
  7. 7

    Obtain registration or generation authorization

    The act depends on source, capacity and regulatory regime.

    Owner
    Project owner files; ANEEL regulates and issues the applicable act
    Typical timeline
    No single deadline; source, capacity and regime determine the procedure.
    What goes wrong
    The wrong procedure is used or authorization, access and permit data disagree.
  8. 8

    Submit the access request

    Data, studies, schedule, point and capacity through the applicable channel.

    Owner
    Project owner files; the utility or ONS admits and assesses
    Typical timeline
    File early enough for the expected works; blocking issues stop progress.
    What goes wrong
    Documents, dates, registered data and studies do not match.
  9. 9

    Receive the budget or access opinion

    Feasibility, works, technical conditions, schedule and contracted capacity.

    Owner
    The utility issues the distribution budget; ONS issues the transmission opinion
    Typical timeline
    Distribution generally uses 15, 30 or 45 days. Transmission uses 30 days, 120 days or up to 1 year depending on works, without blocking issues.
    What goes wrong
    The regulatory document deadline is mistaken for the total energization schedule.
  10. 10

    Execute use and connection contracts

    Distribution contracts, or CUST with ONS and CCT with the transmission owner.

    Owner
    Project owner and utility, or project owner, ONS and transmission owner
    Typical timeline
    For transmission, execute CUST within 90 days after the opinion; distribution follows the budget and REN 1,000.
    What goes wrong
    Validity or reservation is lost, guarantees start late, or capacity and dates conflict with ramp-up.
  11. 11

    Build, commission and clear operation

    Connection works, protection, metering, telecoms, tests and operational release.

    Owner
    Project owner and grid owner execute their scopes; ONS participates where applicable
    Typical timeline
    Set mainly by required works and the contractual schedule; major reinforcements can take years.
    What goes wrong
    Interfaces lack an owner, or protection, metering, telemetry and tests are left until late.

Large load (demand)

Connection journey — load

From the load profile to commissioning

  1. 1

    Define profile, site and phases

    MW, hourly curve, power quality, redundancy, expansion and required date.

    Owner
    Project owner and designers
    Typical timeline
    Before land and connection commitments; revisit for each project phase.
    What goes wrong
    Only peak MW is disclosed, omitting ramps, harmonics, redundancy and expansion.
  2. 2

    Screen distribution or transmission capacity

    Select voltage and plausible points; generation hosting is not load capacity.

    Owner
    Utility or ONS assesses; the project owner compares alternatives
    Typical timeline
    Early screening; confirmation only in a formal budget or access opinion.
    What goes wrong
    Geographic proximity is mistaken for available electrical capacity.
  3. 3

    Compare TUSD/TUST and locational signals

    Tariff, contracted capacity, charges and the point's long-term economics.

    Owner
    ANEEL approves tariffs; the utility or ONS applies them; the project owner models them
    Typical timeline
    At site selection and again before contractual commitments.
    What goes wrong
    The model uses an old tariff cycle or ignores contracted capacity and charges.
  4. 4

    Define MUST or contracted demand

    Transmission uses MUST; distribution uses demand under the applicable contract.

    Owner
    Project owner proposes; ONS or the utility assesses and contracts the applicable amount
    Typical timeline
    Defined before access and consolidated in the contract; phase it with the project ramp-up.
    What goes wrong
    Under-contracting creates exceedance exposure; over-contracting pays for idle capacity.
  5. 5

    Perform electrical studies

    Power flow, contingencies, short circuit, quality and applicable dynamics.

    Owner
    Project owner performs studies; ONS or the utility assesses them
    Typical timeline
    Iterative; repeat when the model, plant/load or point changes.
    What goes wrong
    An outdated model, mismatched assumptions or missing required cases creates a blocking issue.
  6. 6

    Run environmental and land permitting

    Scope, studies and permits with the competent environmental authority.

    Owner
    Project owner before the competent federal, state or municipal authority
    Typical timeline
    Variable by location, impact, study and requests for additional information; start early.
    What goes wrong
    An assumed exemption or early permit is mistaken for full permission to build and operate.
  7. 7

    Submit the access request

    Data, studies, schedule, point and capacity through the applicable channel.

    Owner
    Project owner files; the utility or ONS admits and assesses
    Typical timeline
    File early enough for the expected works; blocking issues stop progress.
    What goes wrong
    Documents, dates, registered data and studies do not match.
  8. 8

    Receive the budget or access opinion

    Feasibility, works, technical conditions, schedule and contracted capacity.

    Owner
    The utility issues the distribution budget; ONS issues the transmission opinion
    Typical timeline
    Distribution generally uses 15, 30 or 45 days. Transmission uses 30 days, 120 days or up to 1 year depending on works, without blocking issues.
    What goes wrong
    The regulatory document deadline is mistaken for the total energization schedule.
  9. 9

    Execute use and connection contracts

    Distribution contracts, or CUST with ONS and CCT with the transmission owner.

    Owner
    Project owner and utility, or project owner, ONS and transmission owner
    Typical timeline
    For transmission, execute CUST within 90 days after the opinion; distribution follows the budget and REN 1,000.
    What goes wrong
    Validity or reservation is lost, guarantees start late, or capacity and dates conflict with ramp-up.
  10. 10

    Build, commission and clear operation

    Connection works, protection, metering, telecoms, tests and operational release.

    Owner
    Project owner and grid owner execute their scopes; ONS participates where applicable
    Typical timeline
    Set mainly by required works and the contractual schedule; major reinforcements can take years.
    What goes wrong
    Interfaces lack an owner, or protection, metering, telemetry and tests are left until late.

Frequently asked questions

How long does a Brazilian grid access opinion take?

For transmission, ONS states 30 days when no works are required, 120 days when reinforcements or improvements are required, and up to one year when expansions are required, provided there are no blocking issues. In distribution, REN 1,000 generally sets 15, 30 or 45 days for the connection budget depending on voltage, installation type and works, with specified grounds for suspension. These are not total build-and-energize timelines.

What is generation export margin?

It indicates how much additional generation a grid point may accommodate in the assessed scenarios without breaching electrical criteria. The ONS dashboard helps compare SIN busbars, but it neither reserves capacity nor replaces the formal access opinion.

Does a generator need MUST?

It depends on the connection. A generator using transmission contracts the Montante de Uso do Sistema de Transmissão (MUST) through its CUST, as established in the access process. Brazilian micro or mini distributed generation under SCEE does not sign a CUST or contract MUST; it follows the utility process.

Does hosting capacity guarantee a distributed-generation connection?

No. Hosting capacity is an indicative feeder screen. Actual conditions, works, costs and timing are set in the utility's connection budget after a complete request is assessed.

What is the difference between TUST and TUSD?

TUST charges for use of transmission; TUSD charges for use of distribution. The applicable tariff depends on the facilities accessed and the user's regulatory status. Both must be assessed together with contracted capacity and location.

Are ANEEL authorization and environmental licensing the same process?

No. ANEEL handles the generation regulatory act, which varies by source, capacity and regime. Environmental licensing is handled by the competent environmental authority and addresses location, impacts and conditions. Both must remain consistent with the grid-access design.